If you've driven through North Port's I-75 interchanges lately, you've seen the new traffic signals blinking away in flash mode. That's about to change. The Florida Department of Transportation (FDOT) says the signals are anticipated to be fully operational on these dates:
- Sumter Boulevard (Exit 182): Monday, November 23, 2026
- Toledo Blade Boulevard (Exit 179): Monday, November 30, 2026
FDOT notes that its schedule can change with weather and unforeseen underground conditions, so the Sumter signals may already be running by the time you read this, or they may take a little longer. Either way, here's what's changing and why it matters if you live here or you're thinking about buying in North Port.
What's being built
This is a $13.4 million FDOT project. It's being led by the state, not the City of North Port. It covers both of our interchanges, and FDOT lists the work under project numbers 452356-1 (Sumter) and 452357-1 (Toledo Blade).
At both interchanges, FDOT is adding:
- Traffic signals at both ramp connections
- Controlled pedestrian crosswalks
- New intersection lighting
- A free-flow on-ramp to northbound I-75 for drivers heading south on the boulevard
At Sumter Boulevard:
- Dual left-turn lanes from northbound Sumter onto northbound I-75
At Toledo Blade Boulevard:
- Dual left-turn lanes from northbound Toledo Blade onto northbound I-75
- Northbound lanes widened to two full lanes through the interchange
How we got here
FDOT held a pre-construction information session on January 6, 2026, at Suncoast Technical College's North Port campus. Early work, like conduit installation and prep for drilled shafts, started the week of April 6, 2026. Since then, a lot of us have gotten used to orange barrels and the occasional overnight detour.
The signals are on, but the work isn't done
Turning on the lights is a big milestone, but crews will keep working at both interchanges, and remaining work continues into 2027. FDOT says that, when necessary, drivers should plan for:
- Lane closures on the I-75 ramps: 10 p.m. to 4 a.m.
- Full ramp closures: 11 p.m. to 5 a.m.
- Single-lane closures on Sumter and Toledo Blade: 9 a.m. to 4 p.m., and 7 p.m. to 7 a.m.
- Double-lane closures: 8 p.m. to 6 a.m.
FDOT posts major closures in its weekly updates. If you use either exit often, it's worth signing up for email alerts on the FDOT project page: https://www.swflroads.com/project/452356-1
You'll find the email update sign-up form linked there, too: https://www.emailmeform.com/builder/form/p79k1bB05Xxryeqh8jiL7U
One more thing: new signals take a little getting used to. For the first few weeks, give yourself some extra following distance and watch for people on foot at the new crosswalks.
What it means if you live here or you're buying here
When my clients look at homes in North Port, one of the first questions is how easy it is to get on and off I-75. It's the road a lot of us use to get to Venice, Sarasota and Fort Myers for work, appointments and errands.
Here's why I think this project is good news:
- Safer, more orderly ramps. Signals and controlled crosswalks bring order to turns that used to depend on finding a gap in traffic.
- Shorter waits for left turns at rush hour. That's one of the main goals of signals and dual left-turn lanes, especially for the northbound I-75 turns.
- Smoother trips north. The new free-flow on-ramps and the extra lanes at Toledo Blade are built to keep traffic moving onto northbound I-75.
I won't put numbers on it. Every commute is different, and it's too early to say exactly how much time anyone will save. But better access to I-75 is the kind of everyday improvement that makes a place easier to live in, and it's worth keeping in mind when you're comparing neighborhoods on either side of the interstate.
If you're weighing a move to North Port, or you're curious how the area is changing near a home you already own, I'm always glad to talk it through.
Also this week: North Port opens its new Utilities complex

On Friday, November 20, 2026, the City of North Port held a ribbon-cutting for its new Richard J. Newkirk Utilities Administration Complex off Pan American Boulevard. The $35 million building brings Utilities Department staff back under one roof after four years of working from different locations around the city, following Hurricane Ian damage to their former building. According to the City, the project was paid for through the Utility Revenue Fund and water and sewer capacity fees. The building is named for Rick Newkirk, who served North Port Utilities for 28 years. Read the City's announcement
Jason "Yoda" Ester, Realtor, RE/MAX Alliance Group
Call or text: 941-376-6626
Email: jasonesterhouses@gmail.com
NorthPortHouses.com
Sources: FDOT project page (https://www.swflroads.com/project/452356-1), City of North Port: FDOT to begin I-75 interchange improvements (https://www.northportfl.gov/News-articles/FDOT-to-begin-I-75-interchange-improvements), and City of North Port: Utilities complex opening (https://www.northportfl.gov/News-articles/North-Port-celebrates-opening-of-new-Utilities-Administration-Complex). Project dates and closures come from FDOT and can change.